Ordinary Council: Agenda

25 January 2022                                                                                                                            Page 1

 

P1#y1

 

 

 

 

 

 

13 January 2022

 

 

 

 

 

Shire of Esperance

 

 

Ordinary Council

NOTICE OF MEETING AND AGENDA

 

An Agenda Briefing Session of the Shire of Esperance will be held at Council Chambers on 18 January 2022 commencing at 1pm to brief Council on the matters set out in the attached agenda.

 

An Ordinary Council meeting of the Shire of Esperance will be held at Council Chambers on 25 January 2022 commencing at 4pm to consider the matters set out in the attached agenda.

 

S Burge

Chief Executive Officer

 


Ordinary Council: Agenda

25 January 2022                                                                                                                            Page 2

 

 

 

 

 

 

DISCLAIMER

 

No responsibility whatsoever is implied or accepted by the Shire of Esperance for any act, omission or statement or intimation occurring during Council or Committee meetings. The Shire of Esperance disclaims any liability for any loss whatsoever and howsoever caused arising out of reliance by any person or legal entity on any such act, omission or statement or intimation occurring during Council or Committee meetings. Any person or legal entity who acts or fails to act in reliance upon any statement, act or omission made in a Council or Committee meeting does so at that person’s or legal entity’s own risk.

 

In particular and without derogating in any way from the broad disclaimer above, in any discussion regarding any planning application or application for a licence, any statement or intimation of approval made by a member or officer of the Shire of Esperance during the course of any meeting is not intended to be and is not to be taken as notice of approval from the Shire of Esperance. The Shire of Esperance warns that anyone who has any application lodged with the Shire of Esperance must obtain and should only rely on written confirmation of the outcome of the application, and any conditions attaching to the decision made by the Shire of Esperance in respect of the application.

 

 

 

ETHICAL DECISION MAKING AND CONFLICTS OF INTEREST

 

Council is committed to a code of conduct and all decisions are based on an honest assessment of the issue, ethical decision-making and personal integrity. Councillors and staff adhere to the statutory requirements to declare financial, proximity and impartiality interests and once declared follow the legislation as required.

 

ATTACHMENTS

 

Please be advised that in order to save printing and paper costs, all attachments referenced in this paper are available in the original Agenda document for this meeting.

 

 

RECORDINGS

 

The Meeting will be livestreamed. The recording will be made publicly available as soon as practical following the meeting.

 


Ordinary Council: Agenda

25 January 2022                                                                                                                            Page 3

 

P54#y1P54#y2Disclosure of Interests

 

P56#y3P56#y4P56#y2P56#y1Agenda Briefing                      Ordinary Council Meeting                 Special Meeting

P57#y1P57#y2Name of Person Declaring an interest

Position                                                               Date of Meeting

This form is provided to enable members and officers to disclose an Interest in the matter in accordance with the regulations of Section 5.65, 5.70 and 5.71 of the Local Government Act 1995 and Local Government (Administration) Regulations 1996 34C.

P60#y2P60#y1Interest disclosed

P61#y1Item No                                     Item Title

P62#y1Nature of Interest

P63#y2P63#y3P63#y1Type of Interest                  Financial                        Proximity                            Impartiality

 

P65#y2P65#y1Interest disclosed

Item No                                     Item Title

P67#y2P67#y1Nature of Interest

P68#y2P68#y3P68#y1Type of Interest                  Financial                        Proximity                            Impartiality

 

P70#y2P70#y1Interest disclosed

P71#y1Item No                                     Item Title

P72#y1Nature of Interest

P73#y2P73#y3P73#y1Type of Interest                  Financial                        Proximity                            Impartiality

 

Declaration

I understand that the above information will be recorded in the Minutes of the meeting and recorded by the Chief Executive Officer in an appropriate Register.

P77#y2
P77#y1
 


P78#y1Signature                                                                                                Date

D20/

 

P79#y1 Disclosure of Interests

P80#y1Notes for Your Guidance

Impact of a Financial Interest (s. 5.65. & s. 67. Local Government Act 1995)

A member who has a Financial Interest in any matter to be discussed at a Council or Committee Meeting, which will be attended by the member, must disclose the nature of the interest:

a.    In a written notice given to the Chief Executive Officer before the Meeting or;

b.    At the Meeting immediately before the matter is discussed.

A member, who makes a disclosure in respect to an interest, must not:

a.    Preside at the part of the Meeting relating to the matter or;

b.    Participate in, or be present during, any discussion or decision making procedure relative to the matter, unless and to the extent that, the disclosing member is allowed to do so under Section 5.68 or Section 5.69 of the Local Government Act 1995.

Interests Affecting Financial Interest

The following notes are a basic guide for Councillors when they are considering whether they have a Financial Interest in a matter.

1.    A Financial Interest, pursuant to s. 5.60A or 5.61 of the Local Government Act 1995, requiring disclosure occurs when a Council decision might advantageously or detrimentally affect the Councillor or a person closely associated with the Councillor and is capable of being measured in money terms. There are expectations in the Local Government Act 1995 but they should not be relied on without advice, unless the situation is very clear.

2.    If a Councillor is a member of an Association (which is a Body Corporate) with not less than 10 members i.e sporting, social, religious etc, and the Councillor is not a holder of office of profit or a guarantor, and has not leased land to or from the club, i.e, if the Councillor is an ordinary member of the Association, the Councillor has a common and not a financial interest in any matter to that Association.

3.    If an interest is shared in common with a significant number of electors and ratepayers, then the obligation to disclose that interest does not arise. Each case needs to be considered.

4.    If in doubt declare.

5.    As stated if written notice disclosing the interest has not been given to the Chief Executive Officer before the meeting, then it must be given when the matter arises in the Agenda, and immediately before the matter is discussed.  Under s. 5.65 of the Local Government Act 1995 failure to notify carries a penalty of $10 000 or imprisonment for 2 years.

6.    Ordinarily the disclosing Councillor must leave the meeting room before discussion commences. The only exceptions are:

6.1  Where the Councillor discloses the extent of the interest, and Council carries a motion under s.5.68(1)(b)(ii) of the Local Government Act 1995; or

6.2  Where the Minister allows the Councillor to participate under s.5.69(3) of the Local Government Act 1955, with or without conditions.

 


 

P100#y2P100#y1

Interests Affecting Proximity (s. 5.60b Local Government Act 1995)

1.   For the purposes of this subdivision, a person has a proximity interest, pursuant to s.5.60B of the Local Government Act 1995, in a matter if the matter concerns;

  1. a proposed change to a planning scheme affecting land that adjoins the person’s land; or
  2. a proposed change to the zoning or use of land that adjoins the person’s land; or
  3. a proposed development (as defined in section 5.63(5)) of land that adjoins the person’s land.

2.   In this section, land (the proposal land) adjoins a person’s land if;

  1. The proposal land, not being a thoroughfare, has a common boundary with the person’s land; or
  2. The proposal land, or any part of it, is directly across a thoroughfare from, the person’s land; or
  3. The proposal land is that part of a thoroughfare that has a common boundary with the person’s land.

3.   In this section a reference to a person’s land is a reference to any land owned by the person or in which the person has any estate or interest.

 

Interests Affecting Impartiality

Definition: An interest, pursuant to Regulation 11 of the Local Government (Rules of Conduct) Regulations 2007, that would give rise to a reasonable belief that the impartiality of the person having the interest would be adversely affected, but does not include an interest as referred to in Section 5.60 of the ‘Act’.

A member who has an Interest Affecting Impartiality in any matter to be discussed at a Council or Committee Meeting, which will be attended by the member, must disclose the nature of the interest;

a.    In a written notice given to the Chief Executive Officers before the Meeting or;

b.    At the Meeting, immediately before the matter is discussed

 

Impact of an Impartiality disClosure

There are very different outcomes resulting from disclosing an interest affecting impartiality compared to that of a financial interest. With the declaration of a financial interest, an elected member leaves the room and does not vote.

With the declaration of this type of interest, the elected member stays in the room, participates in the debate and votes. In effect then, following disclosure of an interest affecting impartiality, the member’s involvement in the Meeting continues as if no interest existed.

 

 


Ordinary Council: Agenda

25 January 2022                                                                                                                            Page 8

 

 

 

TABLE OF CONTENTS

 

 

1.         OFFICIAL OPENING   9

2.         ATTENDANCE  9

3.         APOLOGIES & NOTIFICATION OF GRANTED LEAVE OF ABSENCE  9

4.         APPLICATIONS FOR LEAVE OF ABSENCE  9

5.         ANNOUNCEMENTS BY THE PERSON PRESIDING WITHOUT DISCUSSION   9

6.         DECLARATION OF MEMBERS INTERESTS  10

6.1      Declarations of Financial Interests – Local Government Act Section 5.60a  10

6.2      Declarations of Proximity Interests – Local Government Act Section 5.60b  10

6.3      Declarations of Impartiality Interests – Admin Regulations Section 34c  10

7.         PUBLIC QUESTION TIME  10

8.         PUBLIC ADDRESSES / DEPUTATIONS  10

9.         Petitions  10

10.      CONFIRMATION OF MINUTES  10

11.      DELEGATES’ REPORTS WITHOUT DISCUSSION   10

12.      MATTERS REQUIRING A DETERMINATION OF COUNCIL  11

12.1   External Services  11

12.1.1    FOGO Implementation Options and Communications and Engagement Strategy  11

12.1.2    Myrup Community Drop Off and Waste Management Transfer Station - Detailed Concept Design  15

12.1.3    Development Application - Change of Use - Dwelling to Holiday House - Lot 1000 (25) Twilight Beach Road, West Beach  20

12.1.4    Development Application - Change of Use - Dwelling to Holiday House - Lot 988 (17) Baleine Drive, Castletown  35

12.1.5    Development Application - Change of Use - Dwelling to Holiday House - S/L 3 (3/1A) The Esplanade, Esperance  49

12.1.6    Cancellation of Request for Management over Reserve 3473  63

12.1.7    Bushfire Mitigation Activity Fund  66

12.2   Asset Management  69

12.2.1    Request for Tanker Jetty Timber 69

12.2.2    BOILC Plant Room and Heating Upgrade Budget Amendment 74

12.3   Corporate & Community Services  78

12.3.1    Policy Review - Executive Services 2022  78

12.3.2    Community Grants Program 2022/2023  81

12.3.3    Lease Renewal Request - The Country Women's Association of Western Australia  98

12.3.4    Financial Services Report - December 2021  104

12.4   Executive Services  155

12.4.1    Information Bulletin - December 2021  155

13.      Reports Of Committees  214

13.1   Minutes of Committees  214

14.      Motions of which Notice has been Given   216

15.      MEMBERS QUESTIONS WITH OR WITHOUT NOTICE  216

16.      URGENT BUSINESS APPROVED BY DECISION   216

17.      MATTERS BEHIND CLOSED DOORS  217

17.1   Lease Surrender Request - Lisa Boardman - Jetty Site 2  217

18.      PUBLIC QUESTION TIME  218

19.      CLOSURE  218

 

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 14

 

 

SHIRE OF ESPERANCE

 

AGENDA

 

Ordinary Council Meeting
TO BE HELD IN Council Chambers ON
25 January 2022

COMMENCING AT 4pm

 

 

1.       OFFICIAL OPENING

The Shire of Esperance acknowledges the Nyungar and Ngadju people who are the Traditional Custodians of this land and their continuing connection to land, waters and community. We pay our respects to Elders past, present and emerging and we extend that respect to other Aboriginal Australians today.

 

2.       ATTENDANCE

Members

Cr I Mickel, AM JP                            President                  Rural Ward

Cr R Chambers                                 Deputy President      Town Ward

Cr J O’Donnell                                                                   Town Ward

Cr S McMullen                                                                   Town Ward

Cr J Obourne                                                                    Town Ward

Cr L de Haas                                                                      Town Ward

Cr W Graham                                                                     Rural Ward

Cr R Horan                                                                        Town Ward

Cr S Flanagan                                                                    Town Ward

Shire Officers

Mr S Burge                                       Chief Executive Officer

Mr M Walker                                     Director Asset Management

Mrs H Phillips                                    Director External Services

Mrs F Baxter                                     Director Corporate & Community Services

Mr R Hindley                                     Manager Strategic Planning & Land Projects

Miss E Hegney                                 Executive Assistant

Miss A Palmer                                   Trainee Administration Assistant – Executive Services

Members of the Public & Press

 

 

3.       APOLOGIES & NOTIFICATION OF GRANTED LEAVE OF ABSENCE

 

 

 

 

4.       APPLICATIONS FOR LEAVE OF ABSENCE

 

 

 

 

5.       ANNOUNCEMENTS BY THE PERSON PRESIDING WITHOUT DISCUSSION

 

 

6.       DECLARATION OF MEMBERS INTERESTS

6.1     Declarations of Financial Interests – Local Government Act Section 5.60a

6.2     Declarations of Proximity Interests – Local Government Act Section 5.60b

6.3     Declarations of Impartiality Interests – Admin Regulations Section 34c

 

 

7.       PUBLIC QUESTION TIME

 

 

 

8.       PUBLIC ADDRESSES / DEPUTATIONS

 

 

 

9.       Petitions

Nil  

 

 

 

10.     CONFIRMATION OF MINUTES

That the Minutes of the Ordinary Council Meeting of the 21 December 2021 be confirmed as a true and correct record.

Voting Requirement                       Simple Majority

 

11.     DELEGATES’ REPORTS WITHOUT DISCUSSION

P244#yIS1


12.     MATTERS REQUIRING A DETERMINATION OF COUNCIL

12.1   External Services

Item: 12.1.1  

FOGO Implementation Options and Communications and Engagement Strategy

Author/s

Scott McKenzie

Manager Council Enterprises

Authorisor/s

Holly Phillips

Director External Services

 

File Ref: D21/43555

 

Applicant

Internal

 

Location/Address

N/A

 

Executive Summary

The intent of the report is for Council to endorse options associated with the implementation of a Food Organics Garden Organics (FOGO) service for the community. The options will form the basis of service, processing and cost assumptions for the FOGO Operational Implementation Plan (OIP) to be presented to Council in February 2022.

 

Further, the report seeks endorsement from Council on the Communications and Engagement Strategy (CES) for the proposed project.

 

Recommendation in Brief

That Council endorse the five (5) recommendations contained within the FOGO Implementation Options Discussion Paper – January 2022 as the basis for the OIP, and to authorize the Chief Executive Officer to pursue grant applications for the potential introduction of the service in the Esperance community.

 

Background

The Community Waste Strategy 2018-2023 (the Strategy) outlines the Shire’s waste management systems and volumes, and waste projections for twenty (20) years up to 2036. The Strategy contains short-term and long-term waste diversion targets for Municipal Solid Waste (MSW) and Total Waste including a target to divert 50% of MSW from landfill by 2025.

 

In 2019 the Shire commissioned Talis Consultants to prepare a Business Case and Implementation Plan for FOGO processing via composting. This plan was presented at Ordinary Council Meeting in May 2019 where Council agreed to commence planning for a third bin system for FOGO materials in Esperance.

 

In November 2020, Council endorsed a due diligence assessment of the Myrup Truck Wash and Liquid Waste Facility at Lot 1885 Myrup Road as the preferred location for a FOGO processing facility. Shire officers were also tasked with preparing a community consultation strategy, and investigating funding and resources to cover an implementation plan for consideration by Council.

 


In May 2021, Council resolved to enter into an agreement with the Shire of Coolgardie for the delivery of waste to the Coolgardie Landfill Facility. With Council deciding to transport residual waste to Coolgardie, the processing of FOGO materials into a compost and/or soil conditioner gained more prominence. 

 

In December 2021, Council received a briefing on community engagement activities, indicative timeframes, and operational matters for consideration. At the Ordinary Council Meeting the same month, Council received the findings of a community-wide survey and noted that overwhelming support exists for a FOGO service in Esperance. 

 

The local processing of FOGO materials can divert approximately 3,500 tonnes of waste from landfill per annum, representing a key opportunity in achieving the Shire’s waste diversion target for 2025. Thus, officers are working towards the provision of a FOGO Operational Implementation Plan (OIP) to Council in February 2022 to enable considered investment decision making for the proposed service.

 

Officer’s Comment

A FOGO Implementation Options Discussion Paper (attached) has been prepared to outline the advantages and disadvantages of five (5) critical areas that will impact on the success of FOGO processing in Esperance.

 

The options cover the following areas:

1.       Standard 3-Bin Bin Service;

2.       Collection Frequency;

3.       Area of Service;

4.       Opt in/Opt Out/Mandatory; and

5.       Kitchen Caddy and Compostable Bags.

 

These operational aspects will impact on the cost of providing the service, and influence the likelihood of acceptance and usability for households. Further, the calculation of these service variables is a core input into the OIP which will be presented to Council in February 2022 for investment decision making on the service.

 

Shire officers are exploring a range of State and Federal Government grant opportunities to assist with the potential introduction of a FOGO service if supported by Council. These opportunities are outlined in the attachment.

 

Further, officers have developed a CES to meet Council’s requirement for community consultation surrounding the proposed project.

 

The CES covers the following six stages of engagement surrounding FOGO:

1.       Early Engagement;

2.       Consultation and Service Design;

3.       Announcement;

4.       Lead Up and Launch;

5.       Ongoing Education; and

6.       Monitoring and Evaluation.

 

Officers have already completed Stage 1 - Early Engagement to raise awareness and obtain feedback on the potential introduction of FOGO.

 

It is important to note that the proposed FOGO introduction date of 1 July 2023 is indicative only and the milestone dates and some activities within the CES will need to be revised. This will occur alongside preparations for the Myrup Community Drop Off and Waste Management Transfer Station as the Shire will not be able to receive FOGO material until the facility is constructed.

 

However, the CES is attached for endorsement which outlines the broad approach for achieving community-wide support and adoption of a FOGO collection service for the Shire.

 

Consultation

Shire Waste Team

 

Financial Implications

There are no immediate financial implications arising from this report. However, the assumptions contained in the attachments will be used to form the basis of calculations for the cost of introducing the service which requires a future decision from Council.

 

Asset Management Implications

Nil

 

Statutory Implications

Nil

 

Policy Implications

Nil

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Natural Environment

A community that is empowered and motivated to minimise waste

Targeted reduction of waste with an emphasis on resource recovery and waste minimisation

 

Corporate Business Plan 2021/22 – 2024/25

N2.4 Investigate food organics and garden organics processing.

 

Environmental Considerations

Nil

 

Attachments

a.

FOGO Implementation Options Discussion Paper - January 2022 - Under Separate Cover

 

b.

FOGO Communications and Engagement Strategy - Under Separate Cover

 

 

 

Officer’s Recommendation

That Council:

1.       Endorse the Communications and Engagement Strategy for the proposed introduction of a Food Organics Garden Organics (FOGO) Service for the Shire of Esperance;

2.       Endorse the five (5) recommendations contained in the FOGO Implementation Options Discussion Paper – January 2022 as the basis for preparing an Operational Implementation Plan for the introduction of a FOGO service, with the recommendations being:

a.      That the Shire provide a standard 3 bin service to comply with the Waste Sorted program and Better Bins Plus: Go FOGO Funding program;

b.      That FOGO be collected on a weekly basis and refuse and recycling on an alternating fortnightly basis;

c.      That the proposed FOGO service cover the same area as the current kerbside recycling service (Esperance and Gibson, plus some surrounds);

d.      That the FOGO program be a mandatory program to be consistent with the waste and recycling services; and

e.      That a Kitchen Caddy and compostable bags be provided without charge to each household replaceable upon request after three (3) years, and compostable bags provided as requested. 

3.       Authorise the Chief Executive Officer to pursue grant opportunities to provide financial assistance for the potential introduction of a FOGO service including, but not limited to:

a.      Better Bins Plus: Go FOGO;

b.      Food Waste to Healthy Soils; and

c.      Building Better Regions Fund – Round 6.

Voting Requirement                       Simple Majority

 

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 15

 

Item: 12.1.2  

Myrup Community Drop Off and Waste Management Transfer Station - Detailed Concept Design

Author/s

Scott McKenzie

Manager Council Enterprises

Authorisor/s

Holly Phillips

Director External Services

 

File Ref: D21/43690

 

Applicant

Internal

 

Location/Address

P390#yIS1

 

Executive Summary

The intent of the report is for Council to consider the Detailed Concept Design for the proposed Community Drop Off and Waste Management Transfer Station (the Facility) at Lot 1885 Myrup Road, Myrup and advance towards Detailed Design of the Facility.

 

Recommendation in Brief

That Council endorse the Detailed Concept Design for the Facility as prepared by GHD Consultants (GHD) and issue a Request for Tender as soon as practical for Detailed Construction Drawings, Quantity Survey and all associated reports required for a Works Approval and License Application under Part V of the Environmental Protection Act 1986 for the Facility. Further, the report recommends that Council make a minimum commitment towards funding the Project to satisfy grant application conditions.

 

Background

At the Ordinary Council Meeting held on 25 May 2021, Council identified the Myrup Truck Wash and Liquid Waste Facility at Lot 1885 Myrup Road, Myrup as the preferred location for the proposed Community Drop Off and Waste Management Transfer Station site (The Facility).

Further, Council requested the Chief Executive Officer engage a suitably qualified consultant to develop a detailed concept design and costings, and to commence the application process for approval with the Department of Water and Environmental Regulation (DWER) criteria for the Facility.

 

GHD were engaged to complete the Detailed Concept Design (the Design) in late June 2021 following a public Request for Quotation process (RFQ-0361).

 

The Design was required to cater for a number of resource recovery activities as well as a transfer station to collect, process and transport residual waste to the Coolgardie Waste Facility for disposal.  The Facility will encompass all activities (other than landfill) currently occurring at Wylie Bay as well as additional activities of Food Organics Garden Organics (FOGO) processing, biosecurity waste incineration, household hazardous waste collection, a quality tip shop, and the compaction and transfer of residual waste.

 

Council was briefed by Shire officers on the delivery of the Design at a session held on 14 December 2021.

 

Officer’s Comment

The attached Detailed Concept Design Report details the information and assumptions relied upon to design the proposed Facility. 

 

The Design includes the following items:

·        Gate House and Weighbridge;

·        Administration Area/Offices/Staff Room;

·        Tip Shop and Education Facility;

·        Dry Materials Recovery Facility (MRF);

·        Community Drop Off;

·        Food & Garden Waste Processing;

·        Metals and Construction & Demolition (C&D) Processing;

·        Waste Transfer Station; and

·        Biosecurity and Medical Waste Incineration.

 

The report highlights that in addition to requiring Detailed Construction Drawings, the Shire requires a number of reports to be prepared for the Facility to successfully apply for Works Approval and a License from DWER for the construction and operation of the facility.

 

These reports include items:

·        Bushfire Attack Level Assessment;

·        Bushfire Management and Emergency Evacuation Plan;

·        Operational and Environmental Management Plan (underway);

·        Traffic Impact Assessment;

·        Stormwater and Leachate Control and Management;

·        Odour Assessment;

·        Acoustic (Noise) Impact Statement;

·        On-site Effluent Disposal; and

·        Clearing Permit (underway).

 

The Design has been developed on the basis of transporting residual waste to Coolgardie in A-Double trucks as identified within the GHD Waste Transport Cost vs Landfilling Assessment (2021) report.

 

Overall, the Facility has been designed for waste to enter from the north (Myrup Rd) in various vehicles (utilities and trailers to large commercial trucks). The waste then transfers from north to south through the Facility before being transferred for landfilling to Coolgardie, recycling in Perth, or being accessed locally as compost/soil conditioner.  

 

Community members will not access the full Facility. Rather, they will able to dispose of their recycling and residual waste within the Community Drop Off area and then leave the site. Inducted contractors will have access to the FOGO processing, Dry MRF, Transfer Station and bulk pads for steel and C&D waste.

 

Consultation

·        Waste Team

·        GHD

 

Financial Implications

The construction costs for the Facility are outlined in Table 1.1. A preliminary engineer’s estimate has been provided by GHD commensurate with the level of the Design. The construction estimate is determined as Class 4 of the Classification Matrix within the Cost Estimate Classification System and therefore can be within -25% to +40%.

 

A more accurate construction estimate will be received once the Detailed Construction Drawings have been prepared. The Engineers estimate excludes fire management infrastructure, building and slab footings, lighting and some minor items.

 

Table 1.1 Construction Costs

P451#yIS1

 

Additional costs will be associated with the preparation of Detailed Construction Drawings, Quantity Survey and all associated reports for the Facility is approximately $400,000 which will be procured via a public tender process.

Council has allocated $10M in the Long-Term Financial Plan in the financial year 2023/24 for the construction of the Facility. The Shire’s Sanitation (Rubbish Removal) Reserve has a budgeted year-end balance of $9.2M for financial year 2021/2022.

 


While there are no immediate financial implications associated with the construction of the Facility it is evident there is a shortfall of allocated Shire funding based on preliminary engineer’s estimates. While these costs will be further interrogated through the Detailed Design process, Council is pursuing contributory funding for the Facility through State and Federal Government sources. This includes the Building Better Regions Fund Infrastructure Projects Stream Round Six which closes on 10 February 2022.

 

In order to satisfy grant application requirements, Council is formally required to make a minimum funding commitment towards the Facility. It is recommended that this contribution is no less than 50% of current construction cost estimates.

 

Asset Management Implications

The construction of the Facility will create a depreciable asset for the Shire that will meet the long-term waste management needs of the region. 

 

Statutory Implications

As a Prescribed Premise under the Environmental Protection Act 1986 (WA), the Shire will require a Works Approval and Licence from DWER under Part V of the Environmental Protection Act 1986 (WA) for the Facility.

 

The categories requiring approval are as follows:

·        FOGO Processing (Category 67A);

·        Material Screening (Category 12);

·        C&D Processing (Category 13);

·        Tyre Storage (Category 57);

·        Incineration (Category 60);

·        Biomedical Waste Incineration (Category 59);

·        Solid Waste Facility (Category 61A); and

·        Solid Waste Depot (Category 62).

 

The Shire is exempt from the requirement to obtain a Development Approval under Section 6 of the Planning and Development Act 2005 as the works constitute a public works. However, the Shire is required to seek building licences under the Building Code of WA and associated Acts and Regulations.

 

Policy Implications

Nil

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Natural Environment

A community that is empowered and motivated to minimise waste

Targeted reduction of waste with an emphasis on resource recovery and waste minimisation

 

Corporate Business Plan 2021/22 – 2024/25

N2.5 Plan for new landfill site

 

Environmental Considerations

Nil


 

Attachments

a.

Myrup Waste Management Transfer Station - Detailed Concept Design - Under Separate Cover

 

 

 

Officer’s Recommendation

That Council;

1)      Endorse the Detailed Concept Design for the Myrup Community Drop Off and Waste Management Transfer Station as prepared by GHD Consultants;

2)      Request the Chief Executive Officer to commence procurement processes, including a Request for Tender, for Detailed Construction Drawings, Quantity Survey and all associated reports required for a Works Approval and Licence Application under Part V of the Environmental Protection Act 1986 for the Facility; and

3)      Approve a contribution of $6,713,728, at minimum, towards the Myrup Community Drop Off and Waste Management Transfer Station Project from the Shire’s Sanitation (Rubbish Removal) Reserve and pursue contributory funding through grant opportunities.

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 20

 

Item: 12.1.3  

Development Application - Change of Use - Dwelling to Holiday House - Lot 1000 (25) Twilight Beach Road, West Beach

Author/s

Richard Hindley

Manager Strategic Planning & Land Projects

 

Peter Wilks

Senior Planning Officer

Authorisor/s

Holly Phillips

Director External Services

 

File Ref: D21/43351

 

Applicant

Thorp Realty on behalf of P Kerr & M Fulton-Peebles

 

Location/Address

Lot 1000 (25) Twilight Beach Road, West Beach

P530#yIS1

 

Executive Summary

That Council consider Development Application 10.2021.4877.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 1000 (25) Twilight Beach Road, West Beach

 

Recommendation in Brief

That Council approve Development Application 10.2021.4877.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 1000 (25) Twilight Beach Road, West Beach subject to conditions.

 

Background

Planning Services received a Development Application for a Change of Use of the existing Dwelling to a Holiday House at Lot 1000 (25) Twilight Beach Road, West Beach (the Property) on 24 November 2021.

 

Holiday House is an ‘A’ use in the Scheme, and has a mandatory advertising requirement to landowners that may be affected by the proposal. In this instance it was determined that all adjoining landowners would be impacted by the proposal and should be notified.

Advertising was undertaken between 24 November 2021 and 15 December 2021 with one (1) objection being received.

 

Officer’s Comment

Lot 1000 (25) Twilight Beach Road, West Beach is zoned Residential R12.5 with a lot size of 914 square metres and is not affected by any special control areas. The Property is in a declared Bushfire Prone Area and the development has been conditioned accordingly.

 

Holiday House means a Single Dwelling on one lot used to provide short term accommodation but does not include a bed and breakfast. Short term accommodation means temporary accommodation either provided continuously or from time to time with no guest accommodated for periods tolling more than three (3) months in any twelve (12) month period.

 

The relevant objective of the Residential zone in this instance is to provide for a range of non-residential uses, which are compatible with and complementary to residential development.

 

Officers consider the proposed Holiday House is compatible with the surrounding residential development so long as it is adequately managed and any conditions applied as part of an approval are adhered to.

 

It is recommended that the proposal be approved with both the Holiday House and Single Dwelling land uses applying to the Property to allow flexibility of use. This is due to previous changes by the Department of Planning, Lands and Heritage requiring the issuance of a separate Development Approval to change a Holiday House back to a Single Dwelling. Issuing an approval with both land uses allows the landowner to switch between using the property as a Single Dwelling and Holiday House as required.

 

The objection received to the application was on the following grounds:

Objection:

Planning Comment:

Noise pollution

Noted. It is acknowledged that noise impact from holiday houses can be an issue. Noise was one of the primary reasons why the Shire of Esperance adopted Local Planning Policy: Holiday Homes to ensure that a local caretaker was provided for Holiday House applications where the landowner themselves may not be able to respond to any issue or complaint arising from the activity including excessive noise.

Traffic and parking

Noted. The section this property on is a slip road with a limited width pavement. Situations may arise which limit traffic flows.

Amenity

Noted. Thorp Realty has confirmed with Planning Services that they will be dealing with any complaints or concerns regarding the operation of the holiday house.

Personal impact

Noted. Thorp Realty has confirmed with Planning Services that they will be dealing with any complaints or concerns regarding the operation of the holiday house.

Comments on Air BNB

Noted. Thorp Realty has confirmed with Planning Services that they will be dealing with any complaints or concerns regarding the operation of the holiday house.

Shortage in long-term rental houses

Noted. This is not a valid planning reason for consideration by officers.

Impacts on prices of long-term rentals

Noted. This is not a valid planning reason for consideration by officers.

 

Option One

That Council approve Development Application 10.2021.4877.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 1000 (25) Twilight Beach Road, West Beach subject to conditions.

 

Option Two

That Council refuse Development Application 10.2021.4877.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 1000 (25) Twilight Beach Road, West Beach for the following reasons:

1.       Amenity impact specifically the social impacts of the development on the adjoining property; and

2.       Insufficient road width for parking of vehicles to maintain safe access and egress to the site.

 

Consultation

Advertising was undertaken between 24 November 2021 and 15 December 2021 with one (1) objection being received.

 

Financial Implications

Application fees totalling $295.00 were received as part of this application.

 

Asset Management Implications

Nil

 

Statutory Implications

Local Planning Scheme No. 24

Pursuant to s.211(1) of the Planning and Development Act 2005, a person aggrieved by the failure of a local government to enforce or implement effectively the observance of a local planning scheme may make representation to the Minister. If the Minister considers it appropriate to do so, representation may be referred to the State Administrative Tribunal for its report and recommendation. Following subsequent actions and recommendation by the SAT the Minister may order the local government to do all things considered necessary for enforcing the observance of the Scheme or any provisions of the Scheme.

In this instance it is considered that the Scheme has been enforced effectively.

 

Policy Implications

Local Planning Policy: Holiday Homes

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Built Environment

New developments that enhance the existing built environment

Encourage innovation and support new development

 

Environmental Considerations

Nil

 

Attachments

a.

Application for Development Approval

 

b.

Objection

 

 

 

Officer’s Recommendation

That Council approve Development Application 10.2021.4877.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 1000 (25) Twilight Beach Road, West Beach subject to the following conditions:

1.       The land and buildings the subject of this approval shall be used for the purposes of Dwelling and Holiday House only and for no other purpose unless otherwise approved in accordance with the provisions of Local Planning Scheme No. 24 (refer below definitions as extracted from Schedule 1 – Definitions of LPS 24 and Appendix 1 of the Residential Design Codes).

a.       Dwelling means a building or portion of a building being used, adapted, or designed or intended to be used for the purpose of human habitation on a permanent basis by a single person, a single family, or no more than six persons who do not comprise a single family.

b.      Holiday House means a single dwelling on one lot used to provide short-term accommodation but does not include a bed and breakfast;

2.       Prior to commencement of use the existing effluent disposal system is to be pumped out and a receipt for the pump-out is to be provided to the Shire of Esperance.

3.       The approved Holiday House must not display a sign exceeding 0.2 square metres in area.

4.       Lighting to assist evacuation and smoke alarms must be hard wired to mains power and be installed in the rooms and associated areas in accordance with Part 3.7 of the Building Code of Australia.

5.       All stormwater and drainage run off from all roofed and impervious areas is to be retained on-site to the satisfaction of the Shire of Esperance (Building Services).

6.       The provision of all services, including augmentation of existing services, necessary as a consequence of any proposed development shall be at the cost of the developer and at no cost to the Shire of Esperance.

7.       The development hereby approved must not create community safety concerns, or otherwise adversely affect the amenity of the subject locality by reason of (or the appearance or emission of) smoke, fumes, noise, vibration, odour, vapour, dust, waste water, waste products or other pollutants.

8.       The proposed operations, during and after construction, are required to comply with the Environmental Protection (Noise) Regulations 1997.

9.       This planning approval relates to the land the subject of the application and the applicant only, and cannot be assigned to any other person or transferred to any other property or premises.

10.     A Section 70A Notification under the Transfer of Land Act 1893 (as amended) must be registered against the Certificate of Title to the land the subject of the proposed development advising the owners and successors in title that:

The subject land occasionally experiences considerable problems with nuisance and disease carrying mosquitoes. These mosquitoes are known carriers of Ross River (RRV) and Barmah Forest (BFV) viruses. Human cases of RRV and BFV diseases occur in some years in this general locality.

The Section 70A Notification is to be registered on the Certificate of Title Prior to OCCUPANCY, with all costs associated with preparing and lodging the Section 70A Notification on the Certificate of Title at the applicant’s/owner’s expense.

11.     In the event that the Manager is unavailable or unable to respond to complaints and issues in a timely manner, an alternate manager is to be nominated to handle any complaints or concerns relating to the property.

12.     A copy of the Holiday Home Management Plan is to be provided to the adjoining landowners.

13.     A Bushfire Attack Level Assessment as undertaken by an Accredited Bush Fire Attack Level (BAL) Assessor is to be supplied prior to commencement of use, with any required upgrade works also to be completed prior to commencement of use.

AND the following advice notes:

1.       The development is to comply with the Building Code of Australia, Building Act 2011, Building Regulations 2012 and the Local Government Act 1995.

2.       It is the responsibility of the developer to search the title of the property to ascertain the presence of any easements and/or restrictive covenants that may apply.

3.       Horizon Power has requested the Shire to advise Applicants that Horizon Power has certain restrictions regarding the installation of conductive materials near its network assets. Applicants are advised to contact Horizon Power’s Esperance office to ascertain whether any of Horizon Power’s restrictions affect their proposed development.

4.       The development the subject of this planning approval is required to comply with the Shire Esperance Health Local Laws 2009.

5.       The developer is to liaise with Shire of Esperance (Statutory Compliance) to determine any requirement for additional approvals for any signage proposed to be erected on site.

6.       Due to issues surrounding control of animals in unfamiliar environments, use of the property as a ‘petsit’ or animal inclusive holiday house is not recommended.

7.       As per NCC 2019 Volume Two – Part 3.7.5 – Smoke Alarms are required on each other storey – The applicant is to ensure a smoke alarm is installed and interconnected in the lower floor garage.

8.       The applicant is to ensure existing Stair Construction is safe and complies with NCC 2019 Volume Two - Part 3.9.1.

9.       The applicant is to ensure existing Barriers & Handrails are safe and comply with NCC 2019 Volume Two - Part 3.9.2.

10.     The applicant is to ensure a window opening is provided with protection if the floor below the window in a bedroom is 2 m or more above the surface beneath in accordance with NCC 2019 Volume Two - Part 3.9.2.6.

11.     The applicant is to ensure a window opening is provided with protection if the floor below the window in a room other than a bedroom is 4 m or more above the surface beneath in accordance with NCC 2019 Volume Two - Part 3.9.2.7.

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 31

 

P660#y1P660#yIS1


P661#yIS1


P662#y1P662#yIS1


P663#yIS1


P664#yIS1


P665#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 34

 

P667#y1P667#yIS1


P668#yIS1


P669#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 35

 

Item: 12.1.4  

Development Application - Change of Use - Dwelling to Holiday House - Lot 988 (17) Baleine Drive, Castletown

Author/s

Richard Hindley

Manager Strategic Planning & Land Projects

 

Peter Wilks

Senior Planning Officer

Authorisor/s

Holly Phillips

Director External Services

 

File Ref: D21/43746

 

Applicant

Stewart Hall & Delia Botha

 

Location/Address

Lot 988 (17) Baleine Drive, Castletown

P693#yIS1

 

Executive Summary

That Council consider Development Application 10.2021.4882.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 988 (17) Baleine Drive, Castletown.

 

Recommendation in Brief

That Council approve Development Application 10.2021.4882.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 988 (17) Baleine Drive, Castletown subject to conditions.

 

Background

Planning Services received a Development Application for a Change of Use of the existing Dwelling to a Holiday House at Lot 988 (17) Baleine Drive, Castletown on 24 November 2021.

 

Holiday House is an ‘A’ use in the Scheme, and has a mandatory advertising requirement to landowners that may be affected by the proposal. In this instance it was determined that all adjoining landowners would be impacted by the proposal and should be notified.

 

Advertising was undertaken between 29 November 2021 and 20 December 2021 with one (1) objection being received.

 

Officer’s Comment

Lot 988 (17) Baleine Drive, Castletown is zoned Residential R20 and is not affected by any special control areas.

 

Holiday House means a Single Dwelling on one lot used to provide short term accommodation but does not include a bed and breakfast. Short term accommodation means temporary accommodation either provided continuously or from time to time with no guest accommodated for periods tolling more than three (3) months in any twelve (12) month period.

 

The relevant objective of the Residential zone in this instance is to provide for a range of non-residential uses, which are compatible with and complementary to residential development.

 

Officers consider the proposed Holiday House is compatible with the surrounding residential development so long as it is adequately managed and any conditions applied as part of an approval are adhered to.

 

It is recommended the proposal be approved with both the Holiday House and Single Dwelling land uses applying to the property to allow flexibility of usage. This is due to previous changes by the Department of Planning, Lands and Heritage requiring the issuance of a separate Development Approval to change a Holiday House back to a Single Dwelling. Issuing an approval with both land uses listed allows for the landowner to switch between using the property as a Single Dwelling and Holiday House as required.

 

The objection received to the application was on the following grounds:

Objection:

Planning Comment:

Noise pollution

Noted. It is acknowledged that noise impact from holiday houses can be an issue. Noise was one of the primary reasons why the Shire of Esperance adopted Local Planning Policy: Holiday Homes to ensure that a local caretaker was provided for Holiday House applications where the landowner themselves may not be able to respond to any issue or complaint arising from the activity including excessive noise.

 

Option One:

That Council approve Development Application 10.2021.4882.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 988 (17) Baleine Drive, Castletown subject to conditions.

 

Option Two

That Council refuse Development Application 10.2021.4882.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 988 (17) Baleine Drive, Castletown for the following reason:

1.       Amenity impact, specifically the social impacts of the development on the adjoining property.

 


Consultation

Advertising was undertaken between 29 November 2021 and 20 December 2021 with one (1) objection being received.

 

Financial Implications

Application fees totalling $295.00 were received as part of this application.

 

Asset Management Implications

Nil

 

Statutory Implications

Local Planning Scheme No. 24

 

Pursuant to s.211(1) of the Planning and Development Act 2005, a person aggrieved by the failure of a local government to enforce or implement effectively the observance of a local planning scheme may make representation to the Minister. If the Minister considers it appropriate to do so, representation may be referred to the State Administrative Tribunal for its report and recommendation. Following subsequent actions and recommendation by the SAT the Minister may order the local government to do all things considered necessary for enforcing the observance of the Scheme or any provisions of the Scheme.

 

In this instance it is considered that the Scheme has been enforced effectively.

 

Policy Implications

Local Planning Policy: Holiday Homes

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Built Environment

New developments that enhance the existing built environment

Encourage innovation and support new development

 

Environmental Considerations

Nil

 

Attachments

a.

Application for Development Approval

 

b.

Neighbour Objection

 

 

 

Officer’s Recommendation

That Council approve Development Application 10.2021.4882.1 for a Change of Use for the existing Dwelling to a Holiday House at Lot 988 (17) Baleine Drive, Castletown subject to the following conditions:

1.       The land and buildings the subject of this approval shall be used for the purposes of Dwelling and Holiday House only and for no other purpose unless otherwise approved in accordance with the provisions of Local Planning Scheme No. 24 (refer below definitions as extracted from Schedule 1 – Definitions of LPS 24 and Appendix 1 of the Residential Design Codes).

·        Dwelling means a building or portion of a building being used, adapted, or designed or intended to be used for the purpose of human habitation on a permanent basis by a single person, a single family, or no more than six persons who do not comprise a single family.

·        Holiday House means a single dwelling on one lot used to provide short-term accommodation but does not include a bed and breakfast;

2.       Prior to commencement of use the existing effluent disposal system is to be pumped out and a receipt for the pump-out is to be provided to the Shire of Esperance.

3.       The approved Holiday House must not display a sign exceeding 0.2 square metres in area.

4.       Lighting to assist evacuation and smoke alarms must be hard wired to mains power and be installed in the rooms and associated areas in accordance with Part 3.7 of the Building Code of Australia.

5.       All stormwater and drainage run off from all roofed and impervious areas is to be retained on-site to the satisfaction of the Shire of Esperance (Building Services).

6.       The provision of all services, including augmentation of existing services, necessary as a consequence of any proposed development shall be at the cost of the developer and at no cost to the Shire of Esperance.

7.       The development hereby approved must not create community safety concerns, or otherwise adversely affect the amenity of the subject locality by reason of (or the appearance or emission of) smoke, fumes, noise, vibration, odour, vapour, dust, waste water, waste products or other pollutants.

8.       The proposed operations, during and after construction, are required to comply with the Environmental Protection (Noise) Regulations 1997.

9.       This planning approval relates to the land the subject of the application and the applicant only, and cannot be assigned to any other person or transferred to any other property or premises.

10.     A Section 70A Notification under the Transfer of Land Act 1893 (as amended) must be registered against the Certificate of Title to the land the subject of the proposed development advising the owners and successors in title that:

The subject land occasionally experiences considerable problems with nuisance and disease carrying mosquitoes. These mosquitoes are known carriers of Ross River (RRV) and Barmah Forest (BFV) viruses. Human cases of RRV and BFV diseases occur in some years in this general locality.

The Section 70A Notification is to be registered on the Certificate of Title Prior to OCCUPANCY, with all costs associated with preparing and lodging the Section 70A Notification on the Certificate of Title at the applicant’s/owner’s expense.

11.     In the event that the Manager is unavailable or unable to respond to complaints and issues in a timely manner, an alternate manager is to be nominated to handle any complaints or concerns relating to the property.

12.     A copy of the Holiday Home Management Plan is to be provided to the adjoining landowners.

13.     This approval for the proposed Change of Use – Dwelling to Holiday House is valid for a period of one (1) year from the date of approval. An extension of time will be automatically granted so long as on no valid complaints are received during the initial (one year) approval period. If a valid objection or complaint is received, this development approval will lapse.

AND the following advice notes:

1.       The development is to comply with the Building Code of Australia, Building Act 2011, Building Regulations 2012 and the Local Government Act 1995.

2.       It is the responsibility of the developer to search the title of the property to ascertain the presence of any easements and/or restrictive covenants that may apply.

3.       Horizon Power has requested the Shire to advise Applicants that Horizon Power has certain restrictions regarding the installation of conductive materials near its network assets. Applicants are advised to contact Horizon Power’s Esperance office to ascertain whether any of Horizon Power’s restrictions affect their proposed development.

4.       The development the subject of this planning approval is required to comply with the Shire Esperance Health Local Laws 2009.

5.       The developer is to liaise with Shire of Esperance (Statutory Compliance) to determine any requirement for additional approvals for any signage proposed to be erected on site.

6.       Due to issues surrounding control of animals in unfamiliar environments, use of the property as a ‘petsit’ or animal inclusive holiday house is not recommended.

Voting Requirement                       Simple Majority

 

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 47

 

P804#y4P804#y3P804#y2P804#y1P804#yIS1


P805#yIS1


P806#y1P806#yIS1


P807#yIS1


P808#y1P808#yIS1


P809#yIS1


P810#yIS1


P811#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 48

 

P813#y2P813#y1P813#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 49

 

Item: 12.1.5  

Development Application - Change of Use - Dwelling to Holiday House - S/L 3 (3/1A) The Esplanade, Esperance

Author/s

Peter Wilks

Senior Planning Officer

Authorisor/s

Holly Phillips

Director External Services

 

File Ref: D22/460

 

Applicant

R A Stephen

 

Location/Address

S/L 3 (3/1A) The Esplanade, Esperance

P832#yIS1

 

Executive Summary

That Council consider Development Application 10.2021.4891.1 for a Change of Use for the existing dwelling to include an Unspecified Use (Short Stay Accommodation) at S/L 3 (3/1A) The Esplanade, Esperance.

 

Recommendation in Brief

That Council refuse Development Application 10.2021.4891.1 for a Change of Use for the existing dwelling to include an Unspecified Use (Short Stay Accommodation) at S/L 3 (3/1A) The Esplanade, Esperance.

 

Background

Planning Services received a Development Application for a Change of Use of the existing dwelling to include an Unspecified Use (Short Stay Accommodation) at S/L 3 (3/1A) The Esplanade, Esperance on 7 December 2021.

 

The proposal is termed Unspecified Use (Short Stay Accommodation) as the proposal does not fall within the existing definitions of Holiday House or Bed and Breakfast, as the proposal is for the renting of only the living area on the lower floor with no food to be provided.

 

As the proposal is for an Unspecified Use (Short Stay Accommodation), with only part of the dwelling to be rented and with the owner to be living on site, it is considered to be similar to a Bed and Breakfast for assessment purposes.

 

Bed and Breakfast applications do not possess a mandatory advertising requirement, however as the proposal is located in a larger strata development it was determined that other strata landowners in the strata complex should be notified.

 

Advertising was undertaken between 7 December 2021 and 7 January 2022 with six (6) objections being received.

 

Officer’s Comment

S/L 3 (3/1A) The Esplanade, Esperance is zoned Residential R40/60 and is by Special Control Area 9 – Coastal Erosion and Inundation Risk.

 

Short term accommodation means temporary accommodation either provided continuously or from time to time with no guest accommodated for periods tolling more than three (3) months in any twelve (12) month period.

 

The relevant objective of the Residential zone in this instance is to provide for a range of non-residential uses, which are compatible with and complementary to residential development.

 

It should also be noted that Local Planning Policy: Holiday Homes includes the following provision:

 

The use of grouped or multiple dwellings will generally not be supported for holiday house accommodation given the potential impacts on adjoining residents, unless all owners/strata owners are in agreement.

 

While the proposal is for Unspecified Use (Short Term Accommodation), and not for a Holiday House, it is noted that the two land uses are very similar and that as such consideration can also be given to this provision.

 

The proposed Unspecified Use (Short Term Accommodation) could be compatible with the surrounding residential development so long as it is adequately managed and any conditions applied as part of an approval are adhered to. However, in this instance due to significant opposition from other owners in the overall strata development, and the impacts on amenity represented by the proposal, the officers recommend refusal of the Development Application.

 

The objections received to the application were on the following grounds:

Objection:

Planning Comment:

Noise pollution

Noted. It is acknowledged that noise impact from holiday houses, air BNBs and similar can be an issue. In this instance the applicant has indicated he will be living on site and therefore will be able to handle any issues as they arise.

Waste Disposal

Noted. The property owner/manager would be responsible for ensuring that all wastes are properly disposed of, however Planning Officers acknowledge that wastes disposed of in other people bins without their knowledge may be left for extended periods if those individuals are not on their properties.

Limited parking

Noted. The unit in question was approved with a double garage which provides the two car parking spaces normally required for a dwelling house, there are also two unsealed car parks in the road reserve which are for visitor parking for the overall development and the subject land is also directly opposite the Jetty Car Park which is frequently busy. Planning Officers do also note that there is frequently overflow car parking on the road reserve between The Esplanade and Dempster Street which indicates that car parking supply may be inadequate for the overall development. As such the Planning Officers acknowledge the concerns regarding vehicle parking.

Security, risk of theft and vandalism, need for security cameras.

Noted. The property owner will living on site and has the responsibility for the handling of any issues that arise including problem tenants and security concerns.

Were tenants to vandalise the property/surrounding area, or steal from nearby landowners this would be a matter for the police.

Any requirement for security cameras would need to be met by the Strata Owners/Strata Management Committee.

Unruly behaviour

Noted. It is acknowledged that unruly and problem behaviour by tenants is always a concern with Short Term Accommodation proposals. In the event that the property owner is unable to handle this type of issue, the WA Police are responsible for handling unruly and problem behaviour.

 

Option One (Officers Recommendation)

That Council refuse Development Application 10.2021.4891.1 for a Change of Use for the existing Dwelling to include an Unspecified Use (Short Term Accommodation) at S/L 3 (3/1A) The Esplanade, Esperance for the following reason:

1.       Amenity impact, specifically the social impacts of the development on the adjoining property.

2.       The majority of owners within the overall strata development have refused to support and/or objected to the proposal.

 


Option Two

That Council approve Development Application 10.2021.4891.1 for a Change of Use for the existing Dwelling to include an Unspecified Use (Short Term Accommodation) at S/L 3 (3/1A) The Esplanade, Esperance subject to the following conditions:

1.       The approved Unspecified Use (Short Term Accommodation) must not display a sign exceeding 0.2 square metres in area.

2.       Lighting to assist evacuation and smoke alarms must be hard wired to mains power and be installed in the rooms and associated areas in accordance with Part 3.7 of the Building Code of Australia.

3.       All stormwater and drainage run off from all roofed and impervious areas is to be retained on-site or directed to a legal point of discharge to the satisfaction of the Shire of Esperance.

4.       The provision of all services, including augmentation of existing services, necessary as a consequence of any proposed development shall be at the cost of the developer and at no cost to the Shire of Esperance.

5.       The development hereby approved must not create community safety concerns, or otherwise adversely affect the amenity of the subject locality by reason of (or the appearance or emission of) smoke, fumes, noise, vibration, odour, vapour, dust, waste water, waste products or other pollutants.

6.       The proposed operations, during and after construction, are required to comply with the Environmental Protection (Noise) Regulations 1997.

7.       This planning approval relates to the land the subject of the application and the applicant only, and cannot be assigned to any other person or transferred to any other property or premises.

8.       A Section 70A Notification under the Transfer of Land Act 1893 (as amended) must be registered against the Certificate of Title to the land the subject of the proposed development advising the owners and successors in title that:

The subject land occasionally experiences considerable problems with nuisance and disease carrying mosquitoes. These mosquitoes are known carriers of Ross River (RRV) and Barmah Forest (BFV) viruses. Human cases of RRV and BFV diseases occur in some years in this general locality.

The Section 70A Notification is to be registered on the Certificate of Title Prior to Commencement of use, with all costs associated with preparing and lodging the Section 70A Notification on the Certificate of Title at the applicant’s/owner’s expense.

9.       A Section 70A Notification under the Transfer of Land Act 1893 (as amended) must be registered against the Certificate of Title to the land the subject of the proposed development advising the owners and successors in title that:

VULNERABLE COASTAL AREA - This lot is located in an area likely to be subject to coastal erosion and/or inundation over the next 100 years.

The Section 70A Notification is to be registered on the Certificate of Title prior to the commencement of use, with all costs associated with preparing and lodging the Section 70A Notification on the Certificate of Title at the applicant's/owner's expense.

10.     In the event that the property owner/manager is unavailable or unable to respond to complaints and issues in a timely manner, an alternate manager is to be nominated to handle any complaints or concerns relating to the property.

11.     This approval for the proposed Change of Use – Dwelling to Unspecified Use (Short Term Accommodation) is valid for a period of one (1) year from the date of approval. An extension of time will be automatically granted so long as on no valid complaints are received during the initial (one year) approval period. If a valid objection or complaint is received, this development approval will lapse.

 

AND the following advice notes:

1.       The development is to comply with the Building Code of Australia, Building Act 2011, Building Regulations 2012 and the Local Government Act 1995.

2.       It is the responsibility of the developer to search the title of the property to ascertain the presence of any easements and/or restrictive covenants that may apply.

3.       Horizon Power has requested the Shire to advise Applicants that Horizon Power has certain restrictions regarding the installation of conductive materials near its network assets. Applicants are advised to contact Horizon Power’s Esperance office to ascertain whether any of Horizon Power’s restrictions affect their proposed development.

4.       The development the subject of this planning approval is required to comply with the Shire Esperance Health Local Laws 2009.

5.       The developer is to liaise with Shire of Esperance (Statutory Compliance) to determine any requirement for additional approvals for any signage proposed to be erected on site.

6.       Due to issues surrounding control of animals in unfamiliar environments, use of the property as a ‘petsit’ or animal inclusive holiday house is not recommended.

7.       In accordance with NCC 2019 Volume Two - Part 3.8.3 – A facility for cooking food & Access to clothes washing facilities are required for all occupants.

 

Consultation

Advertising was undertaken between 7 December 2021 and 7 January 2022 with six (6) objections being received.

 

Financial Implications

Application Fees totalling $295.00 were received as part of this application.

 

Asset Management Implications

Nil

 

Statutory Implications

Nil

N/A

The statutory implications associated with this item are

 

Policy Implications

Local Planning Scheme No. 24

Pursuant to s.211(1) of the Planning and Development Act 2005, a person aggrieved by the failure of a local government to enforce or implement effectively the observance of a local planning scheme may make representation to the Minister. If the Minister considers it appropriate to do so, representation may be referred to the State Administrative Tribunal for its report and recommendation. Following subsequent actions and recommendation by the SAT the Minister may order the local government to do all things considered necessary for enforcing the observance of the Scheme or any provisions of the Scheme.

In this instance it is considered that the Scheme has been enforced effectively.

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Built Environment

New developments that enhance the existing built environment

Encourage innovation and support new development

 


Environmental Considerations

Nil

 

Attachments

a.

Application for Development Approval

 

b.

Objection (Siemer)

 

c.

Objection (Morris and Grey)

 

d.

Objection (Wandel)

 

e.

Objection (Black)

 

f.

Objection (Grey)

 

g.

Objection (Bott)

 

 

 

Officer’s Recommendation

That Council refuse Development Application 10.2021.4891.1 for a Change of Use for the existing Dwelling to include an Unspecified Use (Short Term Accommodation) at S/L 3 (3/1A) The Esplanade, Esperance for the following reason:

 

1.       Amenity impact, specifically the social impacts of the development on the adjoining property.

2.       The majority of owners within the overall strata development have refused to support and/or objected to the proposal.

 

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 55

 

P988#yIS1


P989#y2P989#y1P989#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 57

 

P990#y1P990#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 58

 

P991#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 59

 

P992#y2P992#y1P992#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 60

 

P993#y3P993#y2P993#y1P993#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 61

 

P994#y1P994#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 62

 

P995#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 63

 

Item: 12.1.6  

Cancellation of Request for Management over Reserve 3473

Author/s

Richard Hindley

Manager Strategic Planning & Land Projects

Authorisor/s

Holly Phillips

Director External Services

 

File Ref: D21/43758

 

Applicant

Internal (Strategic Planning & Land Projects)

 

Location/Address

Reserve 3473

P1014#yIS1

 

Executive Summary

For Council to consider cancelling the request for Management of Reserve 3473 (Esperance Cemetery).

 

Recommendation in Brief

That Council:

1.       Cancel the request made under Section 41 of the Land Administration Act 1997 to grant management of Reserve 3473 to the Shire of Esperance retaining the current purpose of the Reserve; and

2.       Advise the Department of Planning, Lands and Heritage – Lands of the cancellation of the request for management of Reserve 3473.

 

Background

At the Ordinary Council Meeting in December 2019 Council resolved to:

1.       Request the Minister for Lands under Section 41 of the Land Administration Act 1997 to grant management of Reserve 3473 to the Shire of Esperance retaining the current purpose of the Reserve; and

2.       Commence the road closure process for an unnamed road surrounded by Reserve 3473 in accordance with Section 58 of the Land Administration Act 2007.

 

Following this resolution, a request was forwarded to the Department of Planning, Lands and Heritage – Lands Services seeking to gain the Management of Reserve 3473.

 

Consequently, the Department of Planning, Lands and Heritage – Lands Services (DPLH) advised that the Shire would require a LAA Management Order to exercise powers over Reserve 3473 and consequently enter into an Indigenous Land Use Agreement (ILUA) that provides for the suppression of Native Title rights and interests on the Reserve.

 

Officer’s Comment

Reserve 3473 is subject to non-exclusive Native Title under Determination WAD6097/1998. The Shire approached the DPLH regarding the requirement to enter into an ILUA when Reserve 3473 is shown as an ‘Other Interest’ in Schedule Five of the Native Title under Determination.

 

After internal discussions at DPLH the Shire was advised that the Esperance Cemetery could continue to operate on Reserve 3473 as the Reserve has an Other Interest and the Council is appointed as the Cemeteries Board.

 

Further, the Shire sourced legal opinion on the matter which outlined the Shire could continue to manage the Esperance Cemetery without a management order for the reserve, so long as current uses for the reserve remain in place, as it is required to fulfil its duties under the Cemeteries Act 1986.

 

DPLH’s view is that the continued operation of the Cemetery in the absence of a formal Management Order is at the Shire’s risk. However, it is perceived that there is minimal risk associated with this approach given the Shire is already vested with the care, control and management of the Esperance Cemetery and has no intent to alter uses on the site.

 

It is therefore the view of officers that the Shire should not proactively try to resolve the management of the Reserve.

 

Consultation

Department of Planning, Lands and Heritage – Land Services

 

Financial Implications

N/A

 

Asset Management Implications

N/A

 

Statutory Implications

Land Administration Act 1997

 

Native Title Act 1993 (Cth)

 

WAD6097/1998 Native Title Determination

 

It is acknowledged that Reserve 3473 is subject to non-exclusive Native Title under Determination WAD6097/1998.

 

Paragraph 8 of the Determination provides for the nature and extent of Other Interests (under section 225(c) of the Native Title Act 1993). Paragraph 8 states that 'The nature and extent of other interests in relation to the Determination Area are described in Schedule Five'.

 

Relevantly, Schedule Five of the Determination lists Reserve 3473 - Cemetery as an 'Other Interest'.

 

Reserve 3473 is also shown on page 16 of Schedule Two (Maps of the Determination Area) as 'AREAS THE SUBJECT OF NON-EXCLUSIVE NATIVE TITLE (Areas where native title comprises the rights set out in paragraph 4 of the Determination)'.

 

Paragraph 9 of the Determination provides for the relationship between native title rights and Other Interests (under section 225(d) of the Native Title Act 1993). Paragraph 9 states as follows-

 

'The relationship between the native title rights and interests described in paragraph 4 and the Other Interests is that –

(a)     to the extent that any of the Other Interests are inconsistent with the continued existence, enjoyment or exercise of the native title rights and interests, the native title rights and interests continue to exist in their entirety, but the native title rights and interests have no effect in relation to the Other Interest to the extent of the inconsistency during the currency of the Other Interests; and otherwise

(b)     the existence and exercise of the native title rights and interests do not prevent the doing of any activity required or permitted to be done by or under the Other Interests, and the doing of any activity required or permitted to be done by or under the Other Interests, prevail over the native title rights and interests and any exercise of the native title rights and interests, but, subject to the operation of section 24JB(2) of the Native Title Act 1993, do not extinguish them.'

 

Policy Implications

Nil

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Built Environment

New developments that enhance the existing built environment

Encourage innovation and support new development

 

Environmental Considerations

N/A

 

Attachments

Nil

 

Officer’s Recommendation

That Council:

1.       Cancel the request made under Section 41 of the Land Administration Act 1997 to grant management of Reserve 3473 to the Shire of Esperance retaining the current purpose of the Reserve; and

2.       Advise the Department of Planning, Lands and Heritage – Lands of the cancellation of the request for management of Reserve 3473.

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 66

 

Item: 12.1.7  

Bushfire Mitigation Activity Fund

Author/s

Mel Ammon

Manager Community Support

Authorisor/s

Holly Phillips

Director External Services

 

File Ref: D22/759

 

Applicant

 

Location/Address

·        Reserve 27626, Lot 64 Thompson St, Lots 63, 68, 69, 74 and 75 Stewart St (Skroly’s Park), West Beach

·        Reserve 19624, Lots 33, 34, 501 and 502 Grass Patch Rd, Grass Patch

·        Land bounded by 92, 100, 102 and 108 Starr St, 5, 10, 13, 18, 25, 26, 34, 37 and 42 Alana St and 1, 2, 12 and 22 McLennan St, Gibson

 

Executive Summary

That Council receive $34,500 from the Mitigation Activity Fund to undertake three (3) prescribed burns at West Beach, Grass Patch and Gibson.

 

Recommendation in Brief

That Council receive $34,500 from the Mitigation Activity Fund to undertake three (3) prescribed burns at West Beach, Grass Patch and Gibson.

 

Background

The Mitigation Activity Fund (MAF) provides two (2) rounds of funding annually, to assist with mitigation strategies identified within the Shire’s Bushfire Risk Management Plan (BRMP).

 

The risk to communities from bushfire hazards on State owned land across Western Australia is recognised as a high priority for mitigation. The impact of a bushfire can be reduced through the delivery of mitigation activities that reduce bushfire fuels or improve fire response.

 

Local Governments undertake bushfire risk management planning processes across their jurisdiction to ensure unacceptable bushfire risks are identified and appropriately managed. In many cases, land presenting a significant bushfire risk to communities is Crown land that through the provision of the Local Government Act 1995, falls under the responsibility of Local Governments to manage. It is this Crown land, managed by a Local Government, that the MAF is designated to address.

 

Officer’s Comment

Council endorsed the BRMP in October 2021. An endorsed BRMP, provides eligibility for access to the MAF funding rounds.

 

As such, an application to the MAF round was made to undertake three (3) mitigation/treatment activities, through prescribed burning, on parcels of land at;

·        Reserve 27626, Lot 64 Thompson St, Lots 63, 68, 69, 74 and 75 Stewart St (Skroly’s Park) West Beach - $12,500

·        Reserve 19624, Lots 33, 34, 501 and 502 Grass Patch Rd, Grass Patch - $11,200

·        Land bounded by 92, 100, 102 and 108 Starr St, 5, 10, 13, 18, 25, 26, 34, 37 and 42 Alana St and 1, 2, 12 and 22 McLennan St, Gibson - $10,800

 

The funding application was successful and the Shire will receive $34,500 to undertake these burns by December 2022.

 

Another MAF round of funding will be open in April 2022. If these burns are undertaken and acquitted by this time, the Shire will be eligible for this additional round of funding.

 

A Shire cannot have two (2) grants allocated at one time. Weather permitting, it is the intent to undertake these burns and expend this first round of funding by April 2022 in order to be eligible for the April funding round.

 

Consultation

Office of Bushfire Risk Management

Bush Fire Advisory Committee

 

Financial Implications

The net financial implications arising from this report are Nil. Received MAF funds of $34,500 will be utilised for the prescribed burns totalling $34,500.

Description

Budget Figure

Amended Figure

Variation

01-04090-115-175

 

($700,000)

($734,500)

($34,500)

Fire Mitigation (New)

 

$80,000

$114,500

$34,500

Net result

$0

 

Asset Management Implications

Nil

 

Statutory Implications

Nil

 

Policy Implications

Nil

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Community Connection

A feeling of safety and confidence within our neighbourhoods and a sense of security

Develop and maintain a safe environment for the community

 

Corporate Business Plan 2021/22 – 2024/25

 

Environmental Considerations

Nil

 

Attachments

Nil


 

Officer’s Recommendation

That Council receive $34,500 from the Mitigation Activity Fund to undertake three (3) prescribed burns at West Beach, Grass Patch and Gibson.

Voting Requirement                       Simple Majority

  


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 69

 

12.2   Asset Management

Item: 12.2.1  

Request for Tanker Jetty Timber

Author/s

Mathew Walker

Director Asset Management

Authorisor/s

Shane Burge

Chief Executive Officer

 

File Ref: D22/891

 

Applicant

Shelley Payne MLC

 

Location/Address

92 Dempster Street

 

Executive Summary

For Council to consider the request from the Hon. Shelley Payne MLC for Esperance Tanker Jetty Timber.

 

Recommendation in Brief

That Council sell a Grade 2 Deck Plank to the Hon Shelley Payne MLC for their bench outside 92 Dempster Street, for $75 inclusive of GST.

 

Background

As part of the deconstruction of the Esperance Tanker Jetty, there has been some historic timber salvaged and stockpiled at the Shire Depot. Council has recently adopted Policy ASS 028 Esperance Tanker Jetty Timber that sets out how the Shire will distribute the timber for the community benefit.

 

The Hon. Shelley Payne MLC has requested a Grade 1 or 2 Deck Plank to construct a bench outside her office, please see attached request.

 

Officer’s Comment

The request from the Hon. Shelley Payne MLC meets the requirements of Council Policy ASS 028 Esperance Tanker Jetty Timber “Other” category. It is therefore proposed to sell a Grade 2 Deck Plank for $75 Inc GST in line with the policy. In discussions with the Electorate Office, there is no issue with this.

 

Consultation

Nil

 

Financial Implications

Nil

 

Asset Management Implications

Nil

 

Statutory Implications

Nil

 

Policy Implications

ASS 028: Esperance Tanker Jetty Timber

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Built Environment

New developments that enhance the existing built environment

Encourage innovation and support new development

 

Environmental Considerations

Nil

 

Attachments

a.

Tanker Jetty Timber Application

 

b.

Design and Location of Bench

 

 

 

Officer’s Recommendation

That Council sell a Grade 2 Deck Plank to the Hon. Shelley Payne MLC for their bench outside 92 Dempster Street, for $75 inclusive of GST.

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 71

 

P1273#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 73

 

P1274#yIS1


P1275#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 74

 

Item: 12.2.2  

BOILC Plant Room and Heating Upgrade Budget Amendment

Author/s

Mathew Walker

Director Asset Management

Authorisor/s

Shane Burge

Chief Executive Officer

 

File Ref: D22/1086

 

Applicant

Internal

 

Location/Address

Bay of Isles Leisure Centre - BOILC

 

Executive Summary

For Council to consider a budget amendment for the BOILC heating upgrade.

 

Recommendation in Brief

That Council;

1.       Approves a budget variation for the BOILC heating upgrade as detailed in the following table.

2.       Considers the two deferred projects for inclusion in future budgets.

 

Background

The Bay of Isles Leisure Centre (BOILC) has four pools of substantially different volumes and operating temperatures. Historically, the BOILC has used natural gas to heat the aquatic centre water through three boilers.  Until 2020 the gas required to operate these boilers had been supplied free of charge.  Currently the shire is being charged for the gas consumption at full commercial rates. Given this Council considered alternative methods of pool heating at the November 2020 Ordinary Meeting of Council, and resolved the following:

 

That Council:

1.   Receive the BOILC heating study and the Bay of Isles Leisure Centre Heating Feasibility Study Reports; and

2.   Upgrade the heating at the Bay of Isles Leisure Centre by installing heat pumps to the four pools and the air handling system.

 

Council also committed to a plant room modernisation project in the 2019/20 budget, to upgrade the control system, pumps and chlorine dosing system. The Shire has a current budget of $710,715 to complete both projects.

 

The estimated costs for the BOILC Plant Room and Heating Upgrade has increased due to the following reasons:

Power supply upgrade.

To operate the heat pumps the electrical supply needs to be increased to three times the current supply amount, from 170A to 517A.  This upgrade involves Horizon Power installing a transformer on the Padbury street side of the BOILC site.  The distance of the transformer to the heat pumps means the power supply cable needs to be longer and a of a large diameter, plus the installation will be more complex that the initial concept design.  The magnitude and complexity of the power upgrade has substantially increased the electrical costs of the project


Noise Attenuation

During the detailed design it was identified that due to the proximity of the BOILC is to residents the heat pumps will required to be placed in purpose built enclosures to attenuate the noise.  This noise attenuation was a requirement of the Building Code and the Australian standards.  The costs associated with this was not included in the original estimate. 

Heat Pump Circulation Pipe Insulation

The detail design also identified the benefits of insulating the circulation pipes in reducing heating costs.  The insulation of the pipes involves the construction of a purpose built insulated pipe duct and support structure.  The costs associate with the pipe insulation was not included in the original estimate.

Material costs increase.

Over the past twelve months the cost of materials have continually been increase, in some cases by as much as 80%. These increases have contributed to the increase project cost.

 

A breakdown of the costs to complete the projects is given in attachment A.

 

Officer’s Comment

Given the priority of the BOILC heating upgrade, due to the Esperance Gas Distribution Company ceasing operations of the reticulated natural gas network in Esperance at some stage in the future. It is considered a priority to increase the budget to cover the additional costs to enable the project to be completed.

 

Officers propose to defer two Local Roads and Community Infrastructure projects that are consider a lower priority and reallocate the funding towards the BOILC heating upgrade, these being:

·        GPS CORS Network - $250,000

·        Town Entry Statements - $300,000

Both these project could then be reconsidered for future budgets.

 

The alternative to reallocating these projects would be to fund the additional cost via Shire reserves. The only two reserves suitable are the Building Maintenance and Renewal Reserve and the Priority Projects Reserve, which have approximately $453,000 and $737,000 in them respectfully. Shire Officers would be hesitant to draw down the Building Maintenance and Renewal Reserve as it is prudent to have an enough money in the reserve for any unforeseen building issues.

 

Consultation

Nil

 

Financial Implications

The financial implications arising from this report are detailed in the table below.

Description

Budget Figure

Amended Figure

Variation

BOILC Plant Room and Heating Upgrade

W3136

710,715

1,260,715

550,000

LRCI – GPS CORS Network

W3974

250,000

0

(250,000)

LRCI – Town Entry Statements

W3982

300,000

0

(300,000)

Net result

Nil

 

Asset Management Implications

The Plant Room and Heating Upgrade will substantially lower the ongoing utility operating costs for the BOILC in the order of $100,000 pa.

 

Statutory Implications

Section 6.8 Local Government Act 1995.

Policy Implications

Nil

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Built Environment

Provide infrastructure and places that support the services we provide

Maintain the Shire’s robust asset management practices and maintenance programs

 

Corporate Business Plan 2021/22 – 2024/25

B1.5 Maintain Shire buildings

 

Environmental Considerations

Nil

 

Attachments

a.

BOILC Plant Room and Heating Upgrade Costs Breakdown

 

 

 

Officer’s Recommendation

That Council;

1.       Approves a budget variation for the BOILC Plant Room and Heating Upgrade as detailed in the following table.

Description

Budget Figure

Amended Figure

Variation

BOILC Plant Room and Heating Upgrade

W3136

710,715

1,260,715

550,000

LRCI – GPS CORS Network

W3974

250,000

0

(250,000)

LRCI – Town Entry Statements

W3982

300,000

0

(300,000)

Net result

Nil

2.       Considers the two deferred projects for inclusion in future budgets.

Voting Requirement                       Absolute Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 77

 

P1427#yIS1 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 78

 

12.3   Corporate & Community Services

Item: 12.3.1  

Policy Review - Executive Services 2022

Author/s

Sarah Walsh

Coordinator Governance & Corporate Support

Authorisor/s

Felicity Baxter

Director Corporate & Community Services

 

File Ref: D21/40506

 

Applicant

Internal

 

Location/Address

N/A

 

Executive Summary

For Council to review the section of the Policy Manual that relates to Executive Services.

 

Recommendation in Brief

That Council adopt the Executive Services policies inclusive of amendments, inclusions and deletions as reviewed.

 

Background

A review of Council Policies is recommended to take place every two years, in line with Council elections to ensure that the Policies are in keeping with community expectations, relevance and current requirements.

 

Officer’s Comment

The following is a summary of recommended changes to the existing Executive Services policies. Please refer to Attachment A for details.

Ref No.

Policy Name

Recommended Amendment

EXE 006

Approval to Hold a Civic Reception

No change

EXE 007

Elected Member Entitlements

Update Communications Allowance section in line with current practice

EXE 008

Senior Employees

No change

EXE 011

Legal Representation Cost Indemnification

Remove reference to delegation as this is not a statutory requirement.

EXE 012

Conferring of Honours

Minor change - Formatting and wording of d)

EXE 014

Presentation of a Shire Plaque of the Council Crest

No change

EXE 017

Vandalism Rewards

No change

EXE 019

Risk Management

No change – to be reviewed following change in WHS legislation

EXE 020

External Committee Representation

No change

EXE 021

Community Engagement

Amend Strategic Community Plan and Pulse references, include communication and engagement strategy information,

EXE 022

Public Land Asset Strategy

No change to wording – moves to COR

EXE 023

Use and Storage of Presidential Chain

No change

EXE 024

Civic Centre Hire Fees Not to be Waived

No change to wording – moves to COR

EXE 025

Sporting Association Ground Fees

No change to wording – move to COR

EXE 026

Live Streaming and Recording of Meetings

No change

EXE 027

Electoral Caretaker Period

No change

EXE 028

Cultural Protocols

Move citizenship ceremonies from Welcome to Country section to Acknowledgement section

EXE 029

Attendance at Events

No change

EXE 030

Code of Conduct Behaviour Complaints Management

No change

EXE 031

Elected Member Professional Development

No change

EXE 032

Elected Member Social Media

No change

 

The review of EXE 010: Common Seal policy is still in progress and will be put to Council at a subsequent meeting.

 

It is noted that an absolute majority is required for amendments to the Attendance at Events and Elected Member Professional Development policies.

 

Consultation

Executive Services

 

Financial Implications

Nil

 

Asset Management Implications

Nil

 

Statutory Implications

Local Government Act 1995 – s.2.7(2)(b) Determine the Local Government’s Policies

 

Policy Implications

Nil

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Leadership

Work together to enhance trust, participation and community pride

Actively engage and communicate with the community to ensure informed decision making

 

Corporate Business Plan 2021/22 – 2024/25

Provide leadership and direction to implement the Corporate Business Plan

 

Environmental Considerations

Nil

 

Attachments

a.

Executive Services Reviewed Policies - Under Separate Cover

 

 


 

 

Officer’s Recommendation

That Council adopt the Executive Services policies inclusive of amendments, inclusions and deletions as reviewed.

Voting Requirement                       Absolute Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 81

 

Item: 12.3.2  

Community Grants Program 2022/2023

Author/s

Trevor Ayers

Manager Community & Economic Development

Authorisor/s

Felicity Baxter

Director Corporate & Community Services

 

File Ref: D21/40402

 

Applicant

Internal report

 

Location/Address

N/A

 

Executive Summary

For Council to approve the Community Grants Program Guidelines for the 2022/2023 year and advertise for applications.

 

Recommendation in Brief

That Council:

1.       Endorse the attached 2022/2023 Community Grants Program Guidelines; and

2.       Advertise for applications for the 2022-2023 Community Grants Program during February and March 2022.

3.       Consider recurrent operational funding for The Brass Band, Esperance Community Arts and The Cannery Arts Centre separately to the Community Grants Program.

 

Background

Each year the Community Grants Program is reviewed with amendments made to the guidelines if necessary. This year a significant review has been undertaken to simplify the process and enable a more responsive approach to supporting groups in the community as opportunities for Community Development arise.

 

Officer’s Comment

In previous years the Community Grants Payment has been made up of three categories of annual grants (Development, Events and Assistance) along with the Support category which is open all year. The annual grants are all submitted to Council for approval as part of the annual budget process, while the Shire President and CEO are delegated authority to approve the Support Grants. Table 1 below provides more detail about the four categories available.

 

P1627#yIS1

Table 1

 

Currently any amount over $1,000 has to be applied for as an annual grant during a six week window in February/March. The Council approval process takes place in June and the grant funds are allocated from August onwards (until the following August). This means that some organisations may have to apply up to 16 months ahead for project support. This significant lead-in time makes it difficult for many community organisations to respond to project opportunities as they arise.

 

A suggested improvement to responsiveness is to simplify the program to 2 categories, Small Grants (up to $3,000) and Annual Grants (above $3,000) and increase the amount allocated for the Small Grant category and reduce the annual allocations by that same amount.  This would keep the total Community Grant Program funding at the current level, but result in a two-fold benefit, that funding would be available to groups all year round, as well as a faster turn-around time for the application process.

 

Table 2 below provides a summary of Community Grants issued this year to date and the previous 4 financial years.  It shows that on average, Council issues 25 grants under $1,000 and 7 grants under $3,000 per annum.

 

Summary of Grants Approved per Category

Year

Grants < $1,000 

Grants < $3,000

Grants < $5,000

Grants > $5,000

Total

2021/2022

11*

$8,195

8

$16,070

7

$30,474

8

$254,180

$308,919

2020/2021

28

$24,694

4

$7,960

5

$24,850

10

$214,776

$272,280

2019/2020

27**

$19,958

8

$17,870

5

$23,638

5

$173,300

$234,766

2018/2019

37

$25,332

8

$12,949

5

$21,820

7

$152,796

$212,897

2017/2018

26***

$19,857

6

$10,236

5

$23,500

7

$140,301

$193,894

Average

25.6

$19,607

6.8

$13,017

5.4

$24,856

7.4

$187,071

$244,551

* Year to Date

** A number of approved grants weren't proceeded with due to Covid

*** Support grants were limited to a total pool of $20,000

Table 2

 

Proposed changes to the guidelines is summarized in Table 3 below.

P1720#yIS1

 

Table 3

 


The key points to consider include:

Small Grants

·           Up to $3,000 to be available on an ongoing basis, until the annual budget is allocated.

·           The overall allocation of budget for small grants to be approved with the annual grant’s approval process (traditionally June OCM).

·           Small grants are currently approved under delegated authority by the CEO and President.  It is proposed to either continue this practice or change to one of the following:

1.         Create a review panel of two Councilors (suggest President plus one Councillor with Deputy and one other Councillor to deputize in their absence)

2.         Shire staff to fully manage and report to Council on a monthly basis

(either of these proposals would require a change in delegation).

·           Arts/Sports/Cultural Representation - Representation of Western Australia or Australia by either individuals or teams from Esperance – maximum level of support - $500. Previously this was $200 for State representation and $500 for National / International representation.

Annual Grants

·           Applications over $3,000 continue to be assessed by Council on an annual basis.

·           Organisations will be able to apply for more than one grant (provided only one application is for a purpose other than an event).

 

It is custom for Council to provide annual operational support to the Brass Band, Esperance Community Arts and The Cannery Arts Centre during this process.  As a part of this review, it is recommended to have a separate annual budget allocation for these groups, independent of the Community Grant Program, but continue to apply the same acquittal process. 

 

The current process of Councilors reviewing all grant applications above $1,000 usually takes at least two briefing sessions which results in Council spending significant time reviewing relatively repetitive or small budget allocations. The proposed change would enable Council to focus their time on the larger allocations with the smaller amounts and standard contributions being dealt with at an operational level.

 

This year it is intended to open the annual grant applications on the 1 February and close applications on the 14 March 2022.

 

This timing allows staff sufficient time to review applications, follow up any questions and provide detailed information to Council.

 

Consultation

Community Development Officer,

Community Development & Events Coordinator,

Manager Community & Economic Development,

Director of Corporate and Community Resources and

Manager Community Support.

Councilors briefing (Thursday 16th December)

 

Financial Implications

The amount distributed through the Community Grants Program is at the discretion of Council through the 2022/2023 Budget deliberations and will not be affected by the proposed alterations to the Guidelines.

 

Asset Management Implications

Nil

 

Statutory Implications

Nil

 

Policy Implications

Nil

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Community Connection

A variety of accessible sport, recreation, arts and cultural activities that can be pursued by all

Facilitate and support sport, recreation, arts and cultural activities

 

Environmental Considerations

Nil

 

Attachments

a.

2022/2023 Community Grants Program guidelines

 

 

 

Officer’s Recommendation

That Council;

1.       Endorse the attached 2022/2023 Community Grants Program Guidelines; and

2.       Advertise for applications for the 2022-2023 Community Grants Program during February and March 2022.

3.       Consider recurrent operational funding for the Brass Band, Esperance Community Arts and The Cannery Arts Centre separately to the Community Grants Program.

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 97

 

P1789#yIS1


P1790#yIS1


P1791#yIS1


P1792#yIS1


P1793#yIS1


P1794#yIS1


P1795#yIS1


P1796#yIS1


P1797#yIS1


P1798#yIS1


P1799#yIS1


P1800#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                          Page 98

 

Item: 12.3.3  

Lease Renewal Request - The Country Women's Association of Western Australia

Author/s

Sarah Walsh

Coordinator Governance & Corporate Support

Authorisor/s

Felicity Baxter

Director Corporate & Community Services

 

File Ref: D21/40680

 

Applicant

The Country Women’s Association of Western Australia

 

Location/Address

Lot 304 James Street Esperance, Reserve 23429

P1820#yIS1

 

Executive Summary

For Council to consider entering into a new lease with the Country Women’s Association of Western Australia for Lot 304 James Street Esperance, Reserve 23429.

 

Recommendation in Brief

That Council enters into a new lease with the Country Women’s Association of Western Australia for Lot 304 James Street Esperance, Reserve 23429.

 

Background

Lot 304 James Street is Crown Land and was vested to the Shire of Esperance, with power to lease, for the purpose of ‘Rest Room Country Women’s Association’ in 1952, when the Country Women’s Association (CWA) began leasing the premises. The CWA Hall was built in 1971.

 

The current lease expired in September 2020 and since this time has been operating under the holding over clause due to the development of the James Street Precinct Plan.

 

In 2019, the CWA requested that their lease be renewed for a further 15 years. The longer term has been requested to provide security of tenure for the two branches who are based at the site and to support future investment in the premises.

 

The CWA has recently confirmed that they are still wishing to renew the lease for a further 15 years in accordance with the correspondence received in 2019.

 


Officer’s Comment

The James Street Precinct Plan is now nearing completion and the development of this area is not expected to impact the CWA’s current premises, therefore it is recommended that we proceed with the renewal of the lease.

 

Discussion with Officers has determined that there are no concerns with renewing the lease for this premises, therefore it is recommended to approve the lease request for a further 15 year term.

 

It was noted that the CWA’s building has been constructed across Lot boundaries into Lots 9 and 10 The Esplanade, however the Shire do not have power to lease for these Lots and therefore the lease area will remain being the whole of Lot 304 James Street.

 

Consultation

The Country Women’s Association of WA

Manager Community and Economic Development

Manager Strategic Planning and Land Projects

Coordinator Building Services

Coordinator Environmental Health

Compliance Officer

 

Financial Implications

Annual lease fee $110 Inc GST

Lease preparation fee $132 Inc GST

 

Asset Management Implications

Nil – land only lease

 

Statutory Implications

Local Government Act 1995 – s.5.83 Disposing of Property

Local Government (Functions and General) Regulations 1996 - Section 30(2) Dispositions of property excluded from Act s.3.58

Land Administration Act 1997 – Section 18 Crown Land Transactions that need Minister’s Approval

 

Policy Implications

COR 004: Building and Property Leases

 

Strategic Implications

Strategic Community Plan 2017 - 2027

Growth And Prosperity

Esperance is seen as a destination of choice to live and work

Promote the Esperance lifestyle using environmental, built, cultural and social assets

 

Corporate Business Plan 2021/22 – 2024/25

Manage Shire Leases and Insurance

 

Environmental Considerations

Nil

 

Attachments

a.

Lease Renewal Request - CWA

 

 

 

Officer’s Recommendation

That Council enter into a lease with The Country Women’s Association of Western Australia for Lot 304 James Street Esperance, Reserve 23429, subject to;

1.       Department of Lands’ approval;

2.       Lease term being 15 years;

3.       Annual Lease fee being $110 Inc GST; and

4.       Lease Preparation fee payable of $132 Inc GST.

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 103

 

P1895#yIS1


P1896#y2P1896#y1P1896#yIS1


P1897#y6P1897#y5P1897#y4P1897#y3P1897#y2P1897#y1P1897#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 104

 

Item: 12.3.4  

Financial Services Report - December 2021

Author/s

Beth O'Callaghan

Manager Financial Services

Authorisor/s

Felicity Baxter

Director Corporate & Community Services

 

File Ref: D22/280

 

Attachments

a.

Financial Services Report - December 2021

 

 

Officer’s Recommendation

That Council receive the attached report entitled Monthly Financial Management Report (incorporating the Statement of Financial Activity) for the month of December 2021.

Voting Requirement                       Simple Majority

 


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 120

 

P1923#yIS1

 


P1925#yIS1

 


P1927#yIS1


P1928#yIS1


P1929#yIS1


P1930#yIS1


P1931#yIS1


P1932#yIS1


P1933#yIS1


P1934#yIS1


P1935#yIS1


P1936#yIS1


P1937#yIS1


P1938#yIS1


P1939#yIS1


P1940#yIS1


P1941#yIS1
P1941#yIS2


P1942#yIS1


P1944#yIS1


P1945#yIS1


P1946#yIS1


P1948#yIS1
P1948#yIS2
P1948#yIS3
P1948#yIS4
P1948#yIS5
P1948#yIS6
P1948#yIS7
P1948#yIS8
P1948#yIS9

P1949#yIS1

P1950#yIS1

P1951#yIS1

P1952#yIS1

P1953#yIS1

P1954#yIS1

P1955#yIS1

P1956#yIS1

P1957#yIS1

P1958#yIS1

P1959#yIS1

P1960#yIS1

P1961#yIS1

P1962#yIS1

P1963#yIS1

P1964#yIS1

P1965#yIS1

P1966#yIS1

P1967#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 155

 

12.4   Executive Services

Item: 12.4.1  

Information Bulletin - December 2021

Author/s

Emily Hegney

Executive Assistant

Authorisor/s

Shane Burge

Chief Executive Officer

 

File Ref: D22/278

 

Applicant

Internal

Strategic Implications

Strategic Community Plan 2017 - 2027

Leadership

Work together to enhance trust, participation and community pride

Actively engage and communicate with the community to ensure informed decision making

 

Attachments

a.

Information Bulletin - December 2021

 

b.

Corporate Performance Report - Quarterly - December 2021

 

c.

Delegations Discharge - Corporate Resources

 

d.

Outstanding Resolutions - Quarterly Report

 

 

 

Officer’s Recommendation

That Council accepts:

1.    Information Bulletin - December 2021

2.   Corporate Performance Report - Quarterly - December 2021

3.   Delegations Discharge - Corporate Resources

4.   Outstanding Resolutions - Quarterly Report

Voting Requirement                     Simple Majority

                                       


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 156

 

P2019#yIS1


P2020#yIS1

P2021#yIS1

P2022#yIS1

P2023#yIS1

P2024#yIS1

P2025#yIS1

P2026#yIS1

P2027#yIS1

P2028#yIS1

P2029#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 195

 

P2031#yIS1

P2032#yIS1

P2033#yIS1

P2034#yIS1

P2035#yIS1

P2036#yIS1

P2037#yIS1

P2038#yIS1

P2039#yIS1

P2040#yIS1

P2041#yIS1

P2042#yIS1

P2043#yIS1

P2044#yIS1

P2045#yIS1

P2046#yIS1

P2047#yIS1

P2048#yIS1

P2049#yIS1

P2050#yIS1

P2051#yIS1

P2052#yIS1

P2053#yIS1

P2054#yIS1

P2055#yIS1

P2056#yIS1

P2057#yIS1

P2058#yIS1

P2059#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 196

 

P2061#yIS1


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 213

 

P2062#yIS1

P2063#yIS1

P2064#yIS1

P2065#yIS1

P2066#yIS1

P2067#yIS1

P2068#yIS1

P2069#yIS1

P2070#yIS1

P2071#yIS1

P2072#yIS1

P2073#yIS1

P2074#yIS1

P2075#yIS1

P2076#yIS1

P2077#yIS1

P2078#yIS1 


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 214

 

13.     Reports Of Committees

Item: 13.1  

Minutes of Committees

Author/s

Emily Hegney

Executive Assistant

Authorisor/s

Shane Burge

Chief Executive Officer

 

File Ref: D22/251

 

Attachments

a.

Greater Sports Ground Redevelopment Committee - 23 September 2021 - Under Separate Cover

 

b.

Esperance Roadwise Committee - 21 June 2021 - Under Separate Cover

 

c.

Museum Management Reference Group - 31 May 2021 - Under Separate Cover

 

d.

Local Recovery Committee - 17 November 2020 - Under Separate Cover

 

e.

Reconciliation Action Plan Working Group - 19 October 2020 - Under Separate Cover

 

f.

Streetscape Advisory Committee - 14 October 2020 - Under Separate Cover

 

g.

CEO Recruitment Committee - 21 September 2020 - Under Separate Cover

 

h.

Community Support Sub Committee - 10 September 2020 - Under Separate Cover

 

i.

Esperance Twin Towns Committee - 27 July 2020 - Under Separate Cover

 

j.

Economic Sub Recovery Committee - 19 May 2020 - Under Separate Cover

 

k.

Esperance Visitor Centre Management Committee - 19 December 2018 - Under Separate Cover

 

l.

Scaddan Restoration Reference Group - 27 June 2018 - Under Separate Cover

 

m.

Youth Advisory Council - 26 March 2018 - Under Separate Cover

 

n.

New Landfill Community Reference Group - 2 October 2017 - Under Separate Cover

 

 

 

Officer’s Recommendation

That Council confirm the following most recent minutes of committees which have been disbanded or converted to Working Groups:

1.       Greater Sports Ground Redevelopment Committee - 23 September 2021

2.       Esperance Roadwise Committee - 21 June 2021

3.       Museum Management Reference Group - 31 May 2021

4.       Local Recovery Committee - 17 November 2020

5.       Reconciliation Action Plan Working Group - 19 October 2020

6.       Streetscape Advisory Committee - 14 October 2020

7.       CEO Recruitment Committee - 21 September 2020

8.       Community Support Sub Committee - 10 September 2020

9.       Esperance Twin Towns Committee - 27 July 2020

10.     Economic Sub Recovery Committee - 19 May 2020

11.     Esperance Visitor Centre Management Committee - 19 December 2018

12.     Scaddan Restoration Reference Group - 27 June 2018

13.     Youth Advisory Council - 26 March 2018

14.     New Landfill Community Reference Group - 2 October 2017

Voting Requirement                Simple Majority

 

  


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 216

 

14.     Motions of which Notice has been Given

Nil

 

 

15.     MEMBERS QUESTIONS WITH OR WITHOUT NOTICE

 

 

 

16.     URGENT BUSINESS APPROVED BY DECISION


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 217

 

17.     MATTERS BEHIND CLOSED DOORS

Officer’s Comment:

It is recommended that the meeting is behind closed doors for the following item, in accordance with section 5.23(2) of the Local Government Act 1995.

 

Item: 17.1  

Lease Surrender Request - Lisa Boardman - Jetty Site 2

Confidential Item

This report is considered confidential in accordance with the Local Government Act 1995, as it relates to a matter that if disclosed, would reveal  information about the business, professional, commercial or financial affairs of a person, where the information is held by, or is about, a person other than the local government (Section 5.23(2)(e)(iii)).

 

 

 


Ordinary Council: Agenda

25 January 2022                                                                                                                        Page 218

 

18.     PUBLIC QUESTION TIME

 

 

 

19.     CLOSURE